Press Release: Myers Memorial Pool Renovation Project Bond Vote

Introduction  

Residents of the City of Winooski will have the opportunity to vote on a bond regarding the Myers Memorial Pool Renovation Project during the Vermont State Primary Election, which will take place at the Winooski Senior Center (123 Barlow Street) on August 14th, 2018. Polls will be open from 7 AM to 7 PM.

Bond Vote Details

The officially warned language of this bond vote is as follows: Shall the bonds of the City of Winooski in an amount not to exceed Three Million Nine Hundred Twenty Thousand Dollars ($3,920,000), be issued for the purpose of the planning, design and construction of improvements for the City, known as the Myers Memorial Pool Renovation Project, consisting of planning, design, construction, and reconstruction of the Myers Public Pool, including construction of an addition to the bathhouse building, a filter room, a competition pool, a family pool, and other park improvements?

What does the project cost?

The total cost of this project is $3.92M. If funded solely by Winooski taxpayers, the impact of this project could be up to a $0.082 increase in property taxes (an estimated $185.49 annual increase on a $225,000 home).

Timeline

July 25, 2018 – The Community Services Commission will host an informational meeting and Q & A (6:30 PM @ Winooski City Hall) regarding the bond vote. Light refreshments available. Click here to join the event on Facebook.

August 6, 2018 – A public hearing will be held in conjunction with the regularly scheduled Winooski City Council Meeting (6 PM @ Winooski City Hall). Community members are encouraged to participate. Click here to join the event on Facebook.

August 14, 2018 – The Vermont State Primary Election will take place at the Winooski Senior Center from 7 AM to 7 PM. Click here to join the event on Facebook.

Voting in Winooski

General voting information for Winooski residents can be found at winooskivt.org/voting. To vote early or obtain an absentee ballot, voters can stop by Winooski City Hall on 27 West Allen Street (M – F, 7:30 AM – 4:30 PM). Additional information on early/absentee voting can be found on the Vermont Secretary of State’s website by clicking here.

Project Resources

To view comprehensive project details, please visit winooskivt.org/pool.

Frequently Asked Questions

What is the proposed cost of the pool project?

After completing preliminary engineering, the cost is $3.92M. This is the value approved by the Council to send to a bond vote in August 2018.

How many years will it take to pay off the bond?

The Myers Memorial Pool Renovation Project Bond would be a 20-year bond.

What would the additional property tax increase be?

If funded solely by Winooski taxpayers, the impact of this project could be up to a $0.082 increase in property taxes (an estimated $185.49 annual increase on a $225,000 home).

What is the estimated cost of operation for the new pool for a year?

The City estimates that it would cost approximately $83,000 to operate in the first year of operations.

How many months of the year will the pool be open?

Historically, the Pool has been open from the end of June through August.

How much gross income will be produced by the pool?

We are modeling that the gross income annually would be $12,500.

Contact

Questions regarding the Myers Memorial Pool Renovation Project Bond Vote can be sent to:

Jessie Baker, City Manager: 802 655 6410 / jbaker@winooskivt.org

Ray Coffey, Community Services Director: 802 655 6410 / rscoffey@winooskivt.org